Agreement for Building Where Owner supplies Plot and all materials
The contractor will, if so required by order in writing signed by the owner, alter the design or size of the works and the materials to be used in constructing the same, provided that he shall not be bound to do so unless the sum to be paid for any extras or to be allowed for any omission has been first fixed by agreement between him and the owner and, in default of agreement, the sum to be so paid or allowed shall be settled by ………………
The contractor shall make good any defects, shrinkage or other faults that may appear in the works within six months after their completion.
While the works are in course of construction and until the owner takes over the same, they and all materials or plants used or to be used in constructing the same shall remain at the contractor’s risk and he shall not be entitled to any compensation for injury, to or loss or destruction of, such works or materials arising from any cause whatever.
If the contractor requires any extension of time for completing the works he must apply to the owner within seven days from the date of the occurrence of the event on account of which he desires such extension; and the owner may, if he thinks such request reasonable, grant such extension of time as he may think necessary.
If the owner is at any time dissatisfied with the progress of the work or with the quality of materials used or of the workmanship he may apply to ……. To depute an Engineer to inspect the works, and if such officer certifies in writing that the rate of progress or the materials used or the workmanship or any or all of them is or are unsatisfactory or not in accordance with this agreement, the owner may then enter upon the site of the works and may employ another builder to complete the same and may pay such builder the cost of such completion out of the sum payable to the contractor under this agreement or the balance of such sum if advances have been made to the contractor, and, if such cost is more than such sum of balance, then the contractor will pay the excess to the owner.
Unless the terms are extended under clause (10) hereof, the contractor will complete a portion of the works of the value of not less than Rs….. on or before the …. And will complete the whole work and will remove from the site of the works all plant, scaffolding, unused materials and rubbish and will leave the works and site clean on or before…….
If the contractor fails to comply with the provision of CI. (12) on or before the dates mentioned therein or within such extended time as be permitted in accordance with CI. (13) hereof, he will pay to the owner as liquidated damages a sum of Rs……………for every day’s delay, and the owner may deduct such sum or sums from any money due to the contractor under these presents or may recover it otherwise.